| Supply voltage | Voltage at the charging station’s supply or output terminals, where the tester supports that measurement. | Common nominal supplies include 230 V single-phase and 400 V three-phase in many regions; actual limits depend on the local supply and installation. | Helps identify missing phases, incorrect supply voltage, or other supply problems. |
| Protective earth (PE) continuity | Whether the protective-earth path is present and continuous. | A continuity result is assessed against the test method, installation requirements, and instrument instructions; there is no single pass value for every setup. | A sound earth connection is an important part of protection against electric shock. |
| Control Pilot (CP) state | The control signal used to indicate whether a vehicle is absent, connected, or ready to charge. | For IEC 61851 AC charging, nominal positive CP levels are approximately +12 V (State A), +9 V (State B), and +6 V (State C). | Confirms that the EVSE and tester are exchanging expected connection and charging-state signals. |
| CP PWM duty cycle | The duty cycle of the pilot’s pulse-width-modulated signal, which communicates the available charging current. | For the IEC 61851 current-signalling range of 10%–85%, the advertised current is generally calculated as duty cycle × 0.6 A. For example, 50% indicates 30 A. | Checks that the EVSE communicates its current limit correctly; the vehicle must still respect that limit. |
| Proximity Pilot (PP) coding | Where applicable, the cable’s proximity circuit and its encoded current-carrying rating. | The indicated cable rating depends on the resistor coding and connector system; the tester should report the supported rating or status. | Helps verify that the charging current does not exceed the cable’s indicated capacity. |
| Contactor operation | Whether the EVSE switches its power contacts when the simulated vehicle reaches a charging-ready state. | The output should switch according to the EVSE’s control sequence and applicable test procedure. | Checks that power is enabled only under the expected conditions and is removed when charging is stopped or an unsafe condition is detected. |
| Residual-current protection | Where supported, the response of the charging circuit’s residual-current protection to specified test currents. | Test levels and permitted trip times depend on the protection device, EVSE design, local rules, and the applicable test procedure. Some installations use 30 mA RCD protection and DC fault-current detection. | Assesses an important electrical safety function. The tester’s supported tests must match the installed protection arrangement. |
| Fault simulation | Selected fault conditions, such as a missing PE or an abnormal pilot state, if the tester provides those functions. | The EVSE should respond as specified by its design and the relevant test procedure, commonly by preventing or stopping power delivery. | Shows whether the charger detects certain simulated problems and responds appropriately. |
| Overall functional check | A sequence of simulated connection, ready-to-charge, charging, and stop states. | The tester records whether the EVSE completes the expected sequence and indicates any detected errors. | Provides a practical operational check, but does not replace a full installation inspection or all required electrical tests. |
| Note: Readings and test capabilities vary by tester, EVSE type, connector system, and jurisdiction. Always follow the equipment manuals and applicable electrical safety standards. An EV charger tester is a diagnostic tool; it does not by itself certify an installation. |