| 1 | Calculate the cooling load | Size the chiller from a documented heat-load calculation, including process loads, occupancy, ventilation, equipment, and expected peak conditions. Avoid sizing from floor area alone. | Confirm both peak and typical loads. A load profile helps determine whether one chiller, multiple units, or staged capacity is appropriate. |
| 2 | Choose air-cooled or water-cooled | Air-cooled chillers reject heat directly to outdoor air and generally avoid cooling-tower water use. Water-cooled chillers reject heat through a condenser-water system and cooling tower. | Air-cooled systems can simplify installation where water is limited. Water-cooled systems can be suitable for larger facilities with space, water treatment, and maintenance resources for a tower system. |
| 3 | Match the chiller type to the site | Consider climate, available plant-room or roof space, noise limits, water availability, and maintenance access before selecting a configuration. | Air-cooled, water-cooled, and evaporative-cooled designs have different site and utility requirements. Evaporative systems require water management and suitable operating conditions. |
| 4 | Select a compressor approach | Compare part-load performance, operating hours, capacity range, turndown, and maintenance needs—not just the rated full-load efficiency. | Scroll compressors are commonly used in smaller modular systems; screw compressors serve many medium-to-large applications; centrifugal compressors are often considered for larger, steady cooling loads. Actual suitability depends on the model and design conditions. |
| 5 | Set the required leaving-water temperature | Confirm the process or building design temperature and the required temperature difference across the system. Lower chilled-water temperatures can increase chiller energy use. | A 6°C leaving chilled-water temperature is a common HVAC design example, not a universal requirement. Process cooling may require different temperatures; verify equipment and load specifications. |
| 6 | Review refrigerant suitability | Check local regulations, refrigerant availability, service capability, safety classification, and the equipment manufacturer’s approved refrigerant. Refrigerants are not interchangeable. | Potential choices vary by equipment and jurisdiction. Examples include R-134a, R-513A, R-1234ze(E), ammonia (R-717), and carbon dioxide (R-744); each has distinct performance, safety, and application considerations. |
| 7 | Compare climate impact and safety | Consider refrigerant global-warming potential (GWP), leakage risk, flammability, toxicity, and pressure-related requirements as part of the full system assessment. | For reference, commonly cited 100-year GWP values include approximately 1,430 for R-134a, 631 for R-513A, less than 1 for R-1234ze(E), 0 for ammonia, and 1 for carbon dioxide. Values and regulatory methods can vary; consult current local requirements and safety standards. |
| 8 | Check efficiency at real operating conditions | Request performance data at the specified chilled-water and entering condenser conditions. Evaluate seasonal or integrated efficiency where available. | For air-cooled units, outdoor temperature affects heat rejection. For water-cooled units, cooling-tower and condenser-water conditions affect total plant energy, so compare the complete system where possible. |
| 9 | Plan for part-load operation and redundancy | Match capacity control to the facility’s load pattern and decide what cooling must remain available during maintenance or a unit fault. | Multiple chillers can provide staged capacity and operational redundancy, but the arrangement should be checked against the required reliability level, controls, and lifecycle cost. |
| 10 | Assess lifecycle cost and service needs | Compare purchase, installation, energy, water, maintenance, refrigerant management, and end-of-life costs over the expected service life. | Confirm local technician availability, spare-parts access, water-treatment needs for tower systems, controls integration, and a realistic maintenance plan before final selection. |